Daisy Energy delivered a synchronized generator backup power solution for Etex SA: 2x 1000 kVA Perkins Generator Synchronized Set, with a 2.5 MVA Step-up Transformer 400V/6.6kV.
2024
Install Date
12 weeks
Install Duration
2x 1000 kVA Perkins Generator Synchronized Set
Generators
2.5 MVA Step-up Transformer 400V/6.6kV
Transformer
Etex SA
Project Overview
Install Date: 2024
Install Duration: 12 weeks
Generators: 2x 1000 kVA Perkins Generator Synchronized Set
Transformer: 2.5 MVA Step-up Transformer 400V/6.6kV
Daisy Energy partnered with Etex SA to deliver a turnkey backup power solution, engineered end-to-end from site assessment through installation and commissioning.
“Partnering with Daisy allowed us to consolidate our technology stack and focus on what we do best. The transition was seamless and the ongoing support is exceptional.”
- Operations Manager, Etex SA
Want similar results for your business?
Our specialists are ready to audit your current technology stack and design a solution that works for you.