Back to Case Studies
Case Study
Eureka DIY Project
The Eureka DIY Project was installed in 2017 in Roodepoort. The installation took 8 weeks to complete.
Phase 1 – 136.7 kWp; Phase 2 – 327 kWp; Phase 3 – 220 kWp
System Size
1606.9
Annual Yield
Commercial Grid-Tied
Installation Type
1606.9
Annual kWh/kWp
Eureka DIY

Solution Overview
Installation Date2017
LocationRoodepoort
Installation Duration8 weeks
Client GoalReduce reliance on national grid
Project Info
System SizePhase 1 – 136.7 kWp; Phase 2 – 327 kWp; Phase 3 – 220 kWp
Inverters UsedHuawei
Annual Yield1606.9
Installation TypeCommercial Grid-Tied
Annual kWh \ kWp1606.9

Aluminium casting is an extremely intricate process that relies on a stable power supply. When the power failures occur, the batch becomes un-useable, the pots run the risk of cracking and have to be cleaned out requiring heavy labour. The generator alleviated all the downtime as well as replacement costs.
“Partnering with Daisy allowed us to consolidate our technology stack and focus on what we do best. The transition was seamless and the ongoing support is exceptional.”
- Operations Manager, Eureka DIY Project
Want similar results for your business?
Our specialists are ready to audit your current technology stack and design a solution that works for you.