The Huhtamaki Project was installed in 2021 in Springs. The installation took 14 weeks to complete, including manufacturing.

6x 580 kVA Volvo Generator Set
System Size
3.5MW Synchronised Back-up Generator System (Custom Built with Super Silent Canopies)
Installation Type
14 weeks including manufacturing
Installation Duration

Huhtamaki

Huhtamaki | Completed Energy Project By Daisy Solutions

Solution Overview

Installation Date2021
LocationSprings
Installation Duration14 weeks including manufacturing
Client GoalTo overcome energy supply disruptions and guarantee the plant’s production.

Project Info

System Size6x 580 kVA Volvo Generator Set
Installation Type3.5MW Synchronised Back-up Generator System (Custom Built with Super Silent Canopies)

Huhtamaki | Completed Energy Project By Daisy Solutions

Other Specs:

  • 16000L Automated Diesel re-fueling System
  • DSE Webnet 890 Controller
“Partnering with Daisy allowed us to consolidate our technology stack and focus on what we do best. The transition was seamless and the ongoing support is exceptional.”
- Operations Manager, Huhtamaki

Want similar results for your business?