The Portland Quarry Project was installed in 2021 in Durbanville. The installation took 2 months to complete.
504.9 kWp
System Size
895.2 MWh
Annual Yield
Commercial Grid-Tied
Installation Type
1773
Annual kWh/kWp

Portland Quarry

Solution Overview
Grid-Tied Solar PV.
Installation Date2021
LocationDurbanville
Installation Duration2 months
Client GoalFinancial saving and operational efficiency. Selling power back to the grid.
Project Info
System Size504.9 kWp
Inverters UsedSolis
Annual Yield895.2 MWh
Installation TypeCommercial Grid-Tied
Annual kWh \ kWp1773