Back to Case Studies
Case Study
Signal Hill
The Signal Hill Project was installed in 2020 in Western Cape. The installation took 1 week to complete.
1 x 400 kVA Baudouin Generator set
System Size
1 Week
Installation Duration

Signal Hill

Solution Overview
Installation Date2020
LocationWestern Cape
Installation Duration1 Week
Client GoalThe client was looking for a solution to assist them with load shedding problems they are having. As they are a brewery, they cannot afford to be offline whilst they should be brewing beer, as this is a process that needs to run for several hours.
Project Info
System Size1 x 400 kVA Baudouin Generator set

“Partnering with Daisy allowed us to consolidate our technology stack and focus on what we do best. The transition was seamless and the ongoing support is exceptional.”
- Operations Manager, Signal Hill
Want similar results for your business?
Our specialists are ready to audit your current technology stack and design a solution that works for you.