ETEX SA

Solution Overview
Installation Date
2024
Location
Germiston
Installation Duration
12 weeks
Client Goal
Project Info
System Size
2x 1000 kVA Perkins Generator Synchronized Set
Inverters Used
Annual Yield
Installation Type
2.5 MVA Step-up Transformer 400V/6.6kV
Annual kWh \ kWp

Generators:
2x 1000 kVA Perkins Generator Synchronized Set
Project Type:
2.5 MVA Step-up Transformer 400V/6.6kV
Build:
Custom Built with Standard Canopies, synched to mains with online monitoring